News Flash Home
The original item was published from 11/16/2022 8:24:00 AM to 12/2/2022 12:00:00 AM.

News Flash

News and Events in the Community

Posted on: August 29, 2022

[ARCHIVED] 2022 Road Resurfacing Project

Newsflash Template (48)

2022 Road Resurfacing Project – Phase 1 and Phase 2

Construction Schedule:  Roadway Construction Inc., began phase 1 construction on September 19, 2022. Phase 2 will be bid in spring 2023.

Preliminary Schedule is subject to change due to weather or construction delays. The Town will update regularly, however the schedule may not be completely accurate. This schedule only includes curb ramp construction for now, but will be updated with storm drain work in the next week.

October 3-7

  • Vista Court / Granada Drive
  • Sonora Way / Granada Drive (South)
  • Sonora Drive / Granada Drive (North)

October 10-14 (Underground work only)

  • El Camino Drive / Estrada Lane
  • Granada Drive / Estrada Lane

October 17-21 (Underground work only)

  • Granada Drive / Estrada Lane
  • Estrada Lane / Paloma Drive
  • Granada Drive / El Camino Drive

October 24-28

  • Granada Drive / El Camino Drive
  • El Camino Drive / Paloma Drive
  • Endeavor Drive / Granada Drive
  • Endeavor Drive / Endeavor Cove

October 31-Nov 4

  • 29 Granada Drive - New storm drain improvements
  • Estrada Lane / Paloma Drive - New storm drain improvements
  • 18-37 Paloma Drive - New storm drain improvements
  • 50 El Camino Drive - New storm drain improvements
  • Endeavor Drive at Granada Drive – New curb ramp
  • Prince Royal Drive / Constitution Drive – New curb ramp
  • Prince Royal Drive / Enterprise Drive – New curb ramp
  • Prince Royal Drive / Windward Drive – New curb ramp

November 7-11

  • 18-37 Paloma Drive - New storm drain improvements
  • El Camino Drive / Paloma Drive - New storm drain improvements
  • Prince Royal Drive / Constitution Drive - New storm drain improvements
  • Meadowcreek Drive / Parkview Circle – New curb ramps
  • 39 Parkview Circle – New curb ramps
  • Key Largo Course / Key Largo Cove – New curb ramps and valley gutter

November 14-18

  • El Camino Drive / Granada Drive – New storm drain improvements and curb ramps
  • 18-37 Paloma Drive - New storm drain improvements
  • Endeavor Drive at Granada Drive – New curb ramp
  • El Camino Drive / Paloma Drive - New storm drain improvements
  • Prince Royal Drive / Enterprise Drive – New curb ramp
  • Prince Royal Drive / Windward Drive – New curb ramp
  • Key Largo Course / Key Largo Cove – New curb ramps and valley gutter
  • Ebbtide Passage / Morning Star Course - New curb ramps and valley gutter

November 17-18

  • Crack seal work will be taking place in the Corte Madera Town Park parking lots, Prince Royal Drive, Meadowcreek Drive, Parkview Circle, and various roads in Mariner Cove. No parking signs have been set up where work will take place.

November 21-23

  • Meadowcreek Drive / Parkview Circle – New curb ramps
  • 39 Parkview Circle – New curb ramps
  • Prince Royal Drive / Constitution Drive - New storm drain improvements

November 24-25

  • No construction work during Thanksgiving

Project Description:

The Town has split the 2022 Road Resurfacing Project into two phases after receiving remarkably high bids in July. Phase 1 of the project will include all curb, gutter, sidewalk, ADA curb ramp, and storm drain work and will be rebid immediately. Phase 2 will include all road work including asphalt resurfacing, road sealing, and striping, which will be bid in spring 2023. We appreciate your patience with the change in construction schedule.

The Town opened bids and the project was awarded to the low bidder Roadway Construction, Inc. on August 24, 2022. The first working day is anticipated to be on September 19, 2022. Please check back in the next few weeks for a construction schedule of where the contractor will start work.

In an ongoing effort to maintain the road network in Corte Madera, Public Works will be sealing and resurfacing various roadways listed below on the east side of Corte Madera. Work will include installing ADA curb ramps, improving drainage and making repairs to the storm system, installing new signage, refreshing striping, and other related work.

The Sanitary Disctrict No. 2 recently completed the 2021 Sewer Rehabilitation Project, which replaced sewer mains and lower laterals in the Marin Estates neighborhood. The Town will now be resurfacing those roads as part of the 2022 Road Resurfacing Project. 

The project will include work on the following roads:

  • Creekside Ct
  • Cay Psge
  • Diamond Head Psge
  • Ebbtide Psge
  • El Camino Dr
  • Endeavor Cv
  • Endeavor Dr
  • Estrada Ln
  • Foremast Cv
  • Granada Dr
  • Key Largo Course
  • Key Largo Cove
  • Lanyard Cv
  • Madera Del Presidio Dr
  • Meadow Creek Dr
  • Morning Star Crse
  • Paloma Dr
  • Parkview Cir
  • Prince Royal Dr
  • Seamast Psge
  • Sonora Way
  • Staghound Psge
  • Tradewind Psge
  • Vista Ct

This project is part of the Town’s Capital Improvement Program, which strives to rehabilitate the Sanitary District’s aging sewer infrastructure while also maintaining Town roadways.

Sewer Lateral Information:

For residents living on roads not included in the 2021 Sewer Rehabilitation Project and that have not recently tested or replaced their sewer lateral in the last 3 years, we recommend hiring a plumber to check the sewer lateral and make sure it is in good condition and will last a minimum of 5 years. Once the road resurfacing project is complete, there will be a minimum five-year road moratorium to prolong the life of the new pavement surface. During the moratorium period, residents who request an encroachment permit to cut into the road during that time must demonstrate that the work is necessary and must pay for extensive pavement restoration in an effort to maintain the road’s structural integrity, which can add significant cost to the lateral work.

Be advised that Sanitary District #2 requires that a sewer lateral inspection, which could lead to sewer lateral repairs or replacement, be conducted under the following circumstances:

  1. When a property is sold or when a transfer in property title occurs
  2. When $50,000 in property improvements are performed over a cumulative three year period
  3. If there is a sewer overflow malfunction or public health risk at the property

The letter sent out to residents recommended completing sewer work by July 31, 2022, however due to the phasing of the road resurfacing project, residents will have extra time and should plan to finish sewer lateral repairs by December 31, 2022. The District will waive sewer and encroachment permit fees for property owners who are proactive in testing or replacing their sewer lateral prior to the upcoming capital improvement project.

Useful Links for Sewer Lateral Work

List of Pre-Qualified Sewer Contractors: https://www.townofcortemadera.org/DocumentCenter/View/3807/Pre-Qualified-Contractor-List-For-Public 

2018 Private Sewer Lateral Ordinance Information:

https://townofcortemadera.org/745/Private-Sewer-Lateral-Ordinance 

Available Grant Programs for Private Sewer Laterals:

https://townofcortemadera.org/774/Grant-Programs-for-Private-Sewer-Lateral 

Frequently Asked PSL Questions:

https://townofcortemadera.org/761/Frequently-Asked-Questions 

Project Status: Construction

Project Type(s): Roadway, Storm System, Pedestrian, Traffic
 

If you have further questions regarding this project, please contact Chris Good at (415) 927-5794 or cgood@tcmmail.org.


Additional Info...
Facebook Twitter Email