[ARCHIVED] 2021 Road Rehabilitation Project – UPDATED SCHEDULE

2021 Road Rehabilitation Project

As the Paradise Drive Sidewalk Widening Project nears completion, the Town has begun moving forward with the next phase of our Capital Improvement Program in this area.  Our contractor, Ghilotti Brothers, Inc, started construction for the 2021 Road Rehabilitation Project on September 7th, 2021.  This project involves the installation of ADA curb ramps, improving drainage and making repairs to the storm system, installing new signage, refreshing striping, and other related roadwork.  The 2021 Road Rehabilitation Project involves the complete resurfacing of Paradise Drive from San Clemente Drive to Seawolf Passage in both directions.   Additionally, the following streets within the Marina Village, Mariner Cove and Madera Del Presidio neighborhoods will be resurfaced following the work performed by the 2020 Sewer Rehabilitation Project:

  • Harbor Drive
  • Echo Avenue
  • Yolo Street
  • Edgemar Way
  • Channel Drive
  • Baja Court
  • Pacific Queen Passage
  • Flying Cloud Course
  • Meadow Ridge Drive
  • Ridge Court

Initial work involving identified tree removal, concrete work, drainage repair and the establishment of the ADA ramps will begin upon the start of construction.  Paving and resurfacing segments are scheduled later in the project following infrastructure work expected to continue through end of November (weather permitting).   Prior to the resurfacing of specified streets, effected residents will be notified in advance of the disruption of access by door hangers, no parking barricades, and electronic message boards on effected streets.  

Construction began on September 7th, 2021. Schedule Updated 9/15/2021 as follows: 

  • 9/7 to 9/16 Meadow Ridge Drive and Ridge Court Concrete Work
  • 9/7 to 9/21 Paradise Drive Road Resurfacing
  • 9/16 to 9/23 Meadow Ridge Drive and Ridge Court Road Resurfacing
  • 9/16 to 9/30 Flying Cloud Course Concrete and Drainage Improvements
  • 9/13 to 9/29 Pacific Queen Passage Concrete and Drainage Improvements
  • 9/13 to 11/12 Marina Village Concrete and Drainage Improvements
  • 11/3 to 11/12 Flying Cloud and Pacific Queen Road Resurfacing
  • 11/9 to 11/29 Marina Village Road Resurfacing
  • 11/30 to 12/13 Cleanup work

This schedule is subject to change based on weather and construction delays. The contractor will notify homeowners when work will begin on their street. For more information on the 2021 Road Rehabilitation Project, visit the Town’s project page by clicking here. If you have further questions regarding this work, please contact Senior Civil Engineer Chris Good at (415) 927-5794 or cgood@tcmmail.org.

View the project page and updated schedule
Facebook Twitter Email